background

project details of hydrotech consultants

Wanakbori

Champamathi, Assam

Hayen Hydel Power Company Pvt Ltd
Status: Completed and Working satisfactorily

    Our scope:
  • Preparation of detailed project report
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Project consists of two units of Vertical full Kaplan type turbines connected to synchronous generator through speed increasing gear box.

T. B. Dam, Karnataka

NCL Energy Ltd Hyderabad
Status: Completed and Working satisfactorily

    Our scope:
  • Preparation of detailed project report
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Project consists of three units of horizontal full Kaplan type turbines connected to synchronous generator through speed increasing gear box.

Pottireddy Paadu, Kurnool, A.P.

NCL Energy Ltd Hyderabad
Completed and Working satisfactorily

    Our scope:
  • Preparation of detailed project report
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme 33 kV and 35 kms
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Project consists of three units of horizontal full Kaplan type turbines connected to synchronous generator through speed increasing gear box.

Machkund HEP

Venus Energy Hyderabad

    Our scope:
  • Preparation of detailed project report
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Project is located in Orissa state, down stream of Machkund dam. On hold due to interstate problem.

Dhumajohri project, Orissa

Sharvani Energy Pvt. Ltd Hyderabad

    Our scope:
  • Preparation of detailed project report
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Presently under Execution

Bordikerai Fall, Assam

Brahmaputra Infra Pvt Ltd

    Our scope:
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Presently all four projects are at Completion stage.

Karjan MHS,Gujarat

Kishan Kanaiya Hydro Power Pvt Ltd.
Status:
Completed and Working satisfactorily.

    Our scope:
  • Detailed Project report
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Project consists of two units of horizontal Francis type turbines connected to synchronous generator.

Kattepura MHS, Karnataka

Sai Nireeha Power project Pvt Ltd
Status:
Completed and Working satisfactorily

    Our scope:
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Project consists of three units of horizontal S- type Kaplan turbines connected to synchronous generator through a speed increasing gearbox.

Jatashankari SHEP, Chhatisgarh

Shalivahana Green Energy Limited
Status:
Completed and Working satisfactorily.

    Our scope:
  • Detailed Project Report
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Project consists of Two units of horizontal Francis turbines connected to synchronous generator.

Wanakbori MHS, Gujarat

Oreva Energy Private Limited
Status: Completed and Working satisfactorily.

    Our scope:
  • Detailed Project Report
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Project consists of one unit of horizontal S- type Kaplan turbines connected to synchronous generator.

Rayabasavanna MHS, Karnataka

Khandaleru Power Company Limited
Status: Completed and Working satisfactorily.

    Our scope:
  • Detailed Project Report
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • Bid evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly
  • Commissioning support

Project consists of one unit of horizontal S- type Kaplan turbines connected to synchronous generator

Pahumara MHS, Assam

Agnipa Energo Private Limited

    Our scope:
  • Detailed engineering
  • E & M Bid document
  • Civil works bid document
  • id evaluation report for World Bank/ IREDA
  • Power evacuation scheme
  • Hydro-mechanical equipment design
  • Inspection of turbine and major assembly.
  • Commissioning support

Presently under execution.